- Uncategorized

Calibration of single phase energy meter by phantom loading
by eees.in · April 6, 2023
To calibrate the given single phase wattmeter by phantom loading at UPF and at 0.5pf.
APPARATUS REQUIRED:
- Energy meter
When current rating of the meter under test is high, a test with actual loading arrangements involves considerable waste of power. Phantom loading consists of supplying the pressure circuit with required normal voltage and the current circuit from a low voltage supply. the total power required for testing the meter with phantom loading is comparatively very small.
- Connections are made as shown in diagram
- The rated voltage applied across pressure coil
- Keep the autotransformer at its minimum position and switch on the power supply.
- Adjust the autotransformer for various values of current from minimum to maximum
- Take all meter readings and time taken for 5revolution of E/M disc
- Plot error and calibration curve
At 0.5pf lag
- Connect the pressure coil across N&Y and CC in R phase
- Repeat the same procedure mentioned above
- Plot the error and calibration curve
CIRCUIT DIAGRAM:
OBSERVATION:
The given single phase energy meter is calibrated at UPF and 0.5 lag by phantom loading
You may also like...

Soldering and Desoldering
March 20, 2022
by eees.in · Published March 20, 2022
Calibration of single phase energy meter by direct loading
April 6, 2023
by eees.in · Published April 6, 2023

KPSC Electrician 121/2021
November 22, 2021
by eees.in · Published November 22, 2021
- Next story Characteristics of RTD
- Previous story Calibration of single phase energy meter by direct loading
Recent Posts
- Submerged Arc Welding
- MIG Welding
- TIG welding
- Welding Electrodes
- Basic Welded Joints
Recent Comments
Advertisement.

- _Transformer
- _DC Generator
- _Induction Motor
- _Synchronous Motor
- _Alternator
- _Special Motors
- Measurements
- _Measuring Instruments
- _Potentiometer
- _Measurement of Power
- _Measurement of Energy
- _Measurement of Resistance
- _AC Bridges
- _Transducers
- Power Systems
- _Transmission
- _HVDC Transmission
- _Switchgear
- _Protection
Calibration of Energy Meter - Theory, Procedure & Precautions
Energy meter calibration is a process required to determine and reduce the error when the energy is measured. The errors in the energy meter can be caused by different sources like voltage transformers, current transformers errors due to phase angle, crystal oscillators, etc.
Theory for Energy Meter Calibration :
Energy meters have specified characteristic constants, which give information about the number of revolutions of the disc and the measured energy in joules. These characteristic constants are given by the manufacturer. The experimental setup of the energy meter calibration is shown in the figure below.

Before carrying out the calibration process, different adjustments such as load adjustments, lag adjustments, creep adjustments, etc., are done on the energy meters.
Generally, the number of revolutions is usually high which cannot be taken into measurement in the laboratories. Thus consider the number of revolutions (m) in the disc as 10 for the energy of n joules by using the characteristic constant. The energy (E) can be computed from 'm' is given as,
The meter possesses no error if the energy calibrated for 10 revolutions should be equal to the energy taken by the load for the same amount of revolutions and time. Energy taken by the load or true energy is denoted as E T . The loads applied to the energy meter are varied and the time taken for the 10 revolutions is measured using a stopwatch. The parameters such as voltage, current are observed from the circuit and are tabulated as given below,
For the specified revolutions (i.e., 10) the energy E is constant whereas energy consumed by load E T gets varied and is determined theoretically. Therefore, under various load, the percentage error is calculated as,
Calibration Curve :
Calibration of energy meter can be obtained graphically by plotting the percentage error against load current I. This graphical representation of the calibration process is called a calibration error. At the initial stage, the load current I is zero, and hence no % error because the energies E and E T are zero. The calibration curve is shown in the figure below.

The % error obtained can be positive and negative. The limits of the load current error are easily determined by observing the calibration curve. If the limit is not under desired range then the error can be made to a minimal value by applying different adjustments such as lag, friction, creep adjustments.

Procedure for Energy Meter Calibration :
Make connections as per the circuit diagram. supply rated voltage to the meter which to initially at no-load. check for the connections such that the current coil is in series with the load and the pressure coil is shunted across the voltage supply. note down the voltage, current, and time for the specified revolution of the disc. calibrate the % error theoretically by using the formula., precautions for energy meter calibration :, precautions to be taken while calibrating the energy meter are, the connections made to the meter should not be loose. there should not be any physical contact between the circuit terminals and the observer. the meter should be connected to the load at least for 15 minutes before taking the readings of the meter. this eliminates the friction and temperature error. the readings should be noted down carefully. for accurate and precise errors, the average or mean error should be calibrated by taking more readings..
Do not enter any spam links and messages
Contact Form
- Engineering & Technology
- Electrical Engineering
CALIBRATION OF SINGLE PHASE ENERGY METER

Related documents

Study collections
- measurement
Add this document to collection(s)
You can add this document to your study collection(s)
Add this document to saved
You can add this document to your saved list
Suggest us how to improve StudyLib
(For complaints, use another form )
Input it if you want to receive answer
Calibration and Testing of Single-Phase Energy Meter
Our aim here is to calibrate the given Single-Phase Energy Meter using a precession Wattmeter and stopwatch using or employing phantom loading . The main apparatus required for conducting this practical experiment include:
- Single-Phase Induction type Energy Meter – 240V (5-10)A
- Wattmeter 300V/10A UPF
- Phase Shifting Transformer 440V/440, 500VA
- Single-Phase Variac – 240V / (0-270)V
Procedure for calibration and testing of Single-Phase Energy Meter :-
- Give the connections as per the circuit diagram above.
- Apply 220V A.C to the pressure coil circuit by means of phase shifting transformer.
- Apply a load of 2 Amps by switching on the load.
- Note down the reading of two meters in a given period of time, say 2 minutes.
- Find out the percentage error at this load.
- Now rotate the rotor of phase shifting transformer so that the working power factor (p.f) of the meter is varied.
- For this power factor repeat steps 4 and 5.
Thus we’ve done the testing and calibration of a given Single-Phase energy meter.
Leave a Reply Cancel Reply

IMAGES
VIDEO
COMMENTS
A spring balance is a weighing apparatus used in industries to measure the mass of different loads. It is also used in science experiments as a basic accelerometer. Spring balances are not legal for use in trade because the theory used to c...
Single phase motors can be reversed by either swapping the starting winding or the running winding around but never both. When both windings are swapped around, the motor still runs in the same direction as it did before.
A potential transformer is used in power metering applications, and its design allows it to monitor power line voltages of the single-phase and three-phase variety. A potential transformer is a type of instrument transformer also known as a...
In direct loading both the current and pressure coils are fed from the same supply at rated voltage. Energy meters of high rating when tested by direct loading
Calibration of single phase energy meter by phantom loading · Connections are made as shown in diagram · The rated voltage applied across pressure
Calibration of energy meter can be obtained graphically by plotting the percentage error against load current I. This graphical representation
error i.e. its reading so that same meter can be used for correct measurement of
1. Calibration and Testing of single phase energy Meter. 2. Calibration of dynamometer wattmeter using phantom loading-UPF. 3. Crompton D.C. Potentiometer –
Theory: 3)1 Auto transformer 230/0-270v/5A. (0-10A). MI. 1.
Calibration OF Single Phase Energy Meter BY Direct Loading · 1. Make the circuit connections as shown in figure. · 2. Keep the auto transformer at minimum output
Inductive load CIRCUIT DIAGRAM: THEORY: Generally in the case of A.C circuits as
Give the connections as per the circuit diagram above. · Apply 220V A.C to the pressure coil circuit by means of phase shifting transformer. · Apply a load of 2
Calibration of single phase energy meter and power factor meter by Dr.M Laxmidevi Website Link :- https://www.iare.ac.in/ YouTubeLink
CALIBRATION OF ENERGY METER BY PHANTOM LOADING. AIM. To